<var id="zbznj"></var><var id="zbznj"></var>
<cite id="zbznj"></cite>
<cite id="zbznj"></cite><var id="zbznj"></var><cite id="zbznj"></cite><var id="zbznj"><strike id="zbznj"><listing id="zbznj"></listing></strike></var>
<cite id="zbznj"></cite>
<cite id="zbznj"><video id="zbznj"><thead id="zbznj"></thead></video></cite>
<var id="zbznj"></var><menuitem id="zbznj"></menuitem>
<var id="zbznj"></var>
<var id="zbznj"></var>
<cite id="zbznj"></cite>
<cite id="zbznj"><video id="zbznj"><menuitem id="zbznj"></menuitem></video></cite>
<var id="zbznj"></var>
<cite id="zbznj"><video id="zbznj"></video></cite>
<cite id="zbznj"></cite><ins id="zbznj"></ins>

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO – Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng “Miles” Sun are pleased to announce that underground development at the Kamoa-Kakula Copper Project in the Democratic Republic of Congo (DRC) produced a combined 250,000 tonnes of ore grading 4.85% copper in November from the Kakula and Kansoko mines. The tonnage was 29% higher than achieved in October, while the monthly copper grade increased from 4.01% to 4.85%.

The project’s pre-production surface stockpiles now contain approximately 1.25 million tonnes of high-grade and medium-grade ore at an estimated grade of 3.75% copper. Contained copper in the stockpiles increased by approximately 12,100 tonnes in November – a 55% increase over October’s production – to a cumulative total of more than 46,700 tonnes (the current copper price is approximately US$7,670 a tonne). The project is on track to have approximately three million tonnes of high-grade and medium-grade ore stockpiled on surface, containing more than 125,000 tonnes of copper, prior to the planned start of production in July 2021.

Mr. Friedland and Mr. Sun also noted that underground mine development totalled 2,163 metres in November – only 10 metres shy of establishing another new monthly record. A key milestone was achieved in early November with the joining of Kakula’s main northern and southern access tunnels, establishing access to begin mining Kakula’s high-grade ore in the centre of the orebody grading approximately +8% copper (see figures 1, 2 and 3). The holing event was advanced only from one end for the last few days as a standard safety precaution, which had a minor effect on the metres achieved.

The holing has allowed Kakula’s mining crews to enlarge the development drifts in the centre of the deposit to 7-metres wide by 7-metres high (approximately 23-feet wide by 23-feet high) to take advantage of the excellent copper grades across a thick ore zone – providing a substantial increase in tonnes per metre of development.

November’s development brings total underground development to more than 26.8 kilometres – approximately 9.0 kilometres ahead of schedule. The monthly total of 2,163 metres of underground development in November was comprised of 1,840 metres at the Kakula Mine and 323 metres at the Kansoko Mine, which is located at the Kamoa Deposit – approximately 10 kilometres north of the Kakula Mine.

Mark Farren, Kamoa Copper’s CEO, commented: “November was a great month for mine development. Not only did we join the Kakula’s main access tunnels that now provides a transportation and ventilation connection between the northern and southern declines – a distance of approximately four kilometres, we also achieved record ore production at significantly better copper grades. We expect this production trend to continue as additional mining crews begin working in the centre of the high-grade Kakula orebody. We also saw a sharp increase in copper grades at the Kansoko Mine in November, resulting from ongoing exposure of a rapidly thickening layer of copper-rich siltstone.”

“This month we expect to achieve three key construction milestones – energizing the newly installed 220-kilovolt power line feeding Kamoa-Kakula with hydro-generated electricity from the national grid; synchronization of the first of six turbines at the refurbished Mwadingusha hydropower plant onto the national grid; and commissioning the main surface rock-handling, by-pass conveyor system that will enable the delivery of ore from the Kakula Mine directly to the concentrator plant stockpiles,” Mr. Farren added.

Underground mining crews at Kakula are focused on developing the high grade, drift-and-fill mining blocks in the centre of the orebody. Opening up of the mining footprint for these high grade, drift-and-fill mining areas entails, by necessity, development work in areas of low-, medium- and high-grade ore, and is designed to coincide with the start-up of the processing plant next year. This will allow crews to deliver significant tonnage of high-grade ore directly from Kakula’s underground workings to the processing plant.

While most of the underground development at the Kansoko Mine is in medium-grade ore, in late November mining crews entered the deposit’s initial high-grade ore zone, with 2,100 tonnes of high-grade ore grading 6.66% copper mined by month’s end. Kansoko’s combined medium-grade and high-grade ore mined in November was approximately 33,000 tonnes at an average grade of 3.87% copper. Ongoing exposure of a rapidly thickening siltstone is the reason for a sharp increase in copper grades at Kansoko in November. Siltstone is a rock type with a strong influence on copper mineralization at Kamoa-Kakula.

Kansoko is being developed by training crews and will be a supplemental source of ore for Phase 2 of the project’s development when the Kakula concentrator processing capacity doubles to 7.6 million tonnes per annum (Mtpa) ? currently planned to be commissioned in Q3 2022.

Phase 1 copper production from the Kakula Mine is scheduled to begin in July 2021. Kakula is projected to be the world’s highest-grade major copper mine, with an initial mining rate of 3.8 Mtpa at an estimated average feed grade of more than 6.0% copper over the first five years of operation. Phases 1 and 2 combined are forecast to produce approximately 400,000 tonnes of copper per year. Based on independent benchmarking, the project’s phased expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world’s second largest copper mining complex, with peak annual copper production of more than 800,000 tonnes.

An independent audit of Kamoa-Kakula's greenhouse gas intensity metrics performed by Hatch Ltd., of Mississauga, Canada, confirmed that the project will be among the world's lowest greenhouse gas emitters per unit of copper produced.

Watch a short, fly-over video showcasing the ongoing construction of the Kakula Mine and Phase 1, 3.8 Mtpa concentrator plant: https://vimeo.com/485580022/276d6411df

Left to right:Magloire Kashiba, Production Manager; Jan Strydom, Managerial Leader: Operations; Marna Cloete, Ivanhoe Mines President and CFO; and Pontien Kalala – Section Manager, celebrate the joining of Kakula’s main access tunnels in early November that now provides a transportation and ventilation connection between the northern and southern declines.

In November, the Kamoa-Kakula’s surface construction team achieved five million hours worked without incurring a lost time accident.

Drilling the face of a 7-metre-wide by 7-metre-high development drift in the high-grade centre of the Kakula Deposit.

November’s ore production 29% higher than October, with monthly copper grade increasing from 4.01% to 4.85%; pre-production surface ore stockpiles now total approximately 1.25 million tonnes grading 3.75% copper

In November, mining crews at the Kakula and Kansoko mines mined and transported to surface approximately 250,000 tonnes of ore grading 4.85% copper. This brings the project’s total pre-production high- and medium-grade ore stockpiles to approximately 1.25 million tonnes at an estimated grade of 3.75% copper. An additional 622,000 tonnes of low-grade development ore also has been stockpiled on surface.

November’s ore production is approximately 29% higher than the 194,000 tonnes grading 3.47% copper mined in October, and approximately 89% higher than the 132,000 tonnes grading 3.31% mined in September. The project is well positioned for continued acceleration in the tonnage, as well as an increase in the grade, of ore added to the surface stockpiles as more mining crews commence mining in the higher-grade areas of the Kakula and Kansoko mines.

Chart 1: Cumulative tonnes and grade of pre-production ore stockpiles at the Kakula and Kansoko mines from May 2020 to November 2020.

Chart 2: Growth in contained copper in pre-production ore stockpiles at the Kakula and Kansoko mines from May 2020 to November 2020.

Chart 3: Projected growth in contained copper in the pre-production stockpiles at the Kakula and Kansoko mines up to the planned start of Phase 1 production in July 2021. Dotted line are projections based on the 2020 pre-feasibility study.

The ore being mined from the northern portion of the Kakula Mine is transported to surface via the conveyor system and placed on a blended surface stockpile that now contains approximately 763,000 tonnes grading an estimated 3.93% copper.

Additional, pre-production ore stockpiles are located at the Kakula southern decline (approximately 107,000 tonnes of high-grade ore grading 6.11% copper and 224,000 tonnes of medium-grade ore grading 2.64% copper) and the Kansoko decline (approximately 2,100 tonnes of high-grade ore grading 6.66% copper and 151,000 tonnes of medium-grade ore grading 2.82% copper).

Kakula’s main pre-production stockpiles at the northern declines. The blended stockpiles currently contain approximately 763,000 tonnes grading 3.93% copper.

Kakula southern decline ore stockpiles containing approximately 107,000 tonnes of high-grade ore grading 6.11% copper, and 224,000 tonnes of medium-grade ore grading 2.64% copper.

Kansoko decline ore stockpiles containing 153,000 tonnes grading 2.82% copper, including the initial 2,100 tonnes of high-grade ore grading 6.66% copper.

Figure 1: The overall 13.3-kilometre-long Kakula Deposit overlain on southern Manhattan Island to provide a sense of the scale of the deposit.

Figure 2: The overall 13.3-kilometre-long Kakula Deposit overlain on Paris to provide a sense of the scale of the deposit and underground operations.

Figure 3: Underground development completed at Kakula Mine to November 27, 2020 (in black).

Construction of the initial 3.8-Mtpa concentrator plant and other surface infrastructure rapidly progressing; earthworks and civil works started, and EPCM contract awarded for the second 3.8-Mtpa concentrator plant

Overall progress of Kamoa-Kakula’s first-phase, 3.8 Mtpa mining and milling operation (covering mine infrastructure, concentrator plant and surface infrastructure) now is approximately 63% complete, up from 58% last month. Overall construction of the project’s first-phase 3.8 Mtpa concentrator plant and associated facilities is advancing rapidly and is approximately 35% complete, up from 28% last month. The concentrator plant is expected to be mechanically complete in Q2 2021, with first copper concentrate production scheduled for July 2021.

Civil works for the initial concentrator plant are more than 90% complete, with approximately 28,000 cubic metres of concrete poured to date. All major construction areas have handed over to the steel, mechanical, piping and platework (SMPP) contractor.

More than 2,000 truckloads of equipment have been delivered to site, including the final major pieces of equipment ? two 80-MVA/220-kilovolt (kV) electrical transformers. The transformers have been placed into position at the main Kakula substation and construction of the project’s various electrical substations is progressing well.

All structural steel has been delivered to site, as well as the bulk of the platework and piping. Piping installation has started, as has electrical installation of cable racks and cable installation.

Over 3,000 tonnes of steel (of a total of 5,700 tonnes) has been installed. SMPP erection and installation has commenced in all areas of the concentrator plant and is well advanced. Electrical installation is underway in the milling, flotation and thickener areas.

A recent focus area was to install roof sheeting on the reagent storage building and the concentrate storage building to allow on-site fabrication work to continue during periods of rain.

Steel erection for Kakula’s first phase, backfill paste plant is well advanced with the bulk of the outer structure complete including the installation of the gantry crane, the installation of the two 2000t cement silos is underway. Structural steel erection is scheduled to be completed in early 2021.

The backfill plant will be used to mix tailings from the processing plant with cement to produce paste backfill. The backfill will be pumped back into the mine and used to help support mined-out areas. Approximately one half of the mine’s tailings will be sent back underground, significantly reducing the surface tailings storage.

Construction of the tailings dam is progressing well and is scheduled to be completed well ahead of the required date. Installation of the three tailings lines and the tailings return water line is nearing completion.

The long-lead items for the second 3.8-Mtpa concentrator plant have been ordered and the Phase 2 of the project’s development is underway. Contracts have placed for the earthworks, and civil works and bush clearing has started. The Engineering, Procurement and Construction Management (EPCM) contract also has been signed with ENFI Engineering Corporation, of Beijing, China.

Mark Farren, Kamoa Copper’s CEO (left), and Huang Yingsheng, ENFI’s Director of International Business (right), sign the ECPM contract for Kamoa-Kakula’s Phase 2 concentrator.

A 3D, overhead illustration of the finished the Phase 1, 3.8 Mtpa concentrator plant. The picture immediately below shows the current construction progress (approximately 41% complete).

A 3D illustration of the finished ball mills area for the Phase 1, 3.8 Mtpa concentrator, with the next two ball mills for the recently-initiated Phase 2 concentrator plant shown in magenta. The picture immediately below shows the current construction progress (approximately 59% complete).

A 3D illustration of Kakula’s initial 3.8 Mtpa concentrator plant, with the recently-initiated Phase 2 3.8-Mtpa processing plant shown in magenta. The picture immediately below shows the currentconstruction progress (approximately 48% complete).

A 3D illustration of the initial high-pressure-grinding-rolls (HPGR) stockpile, with the recently-initiated second HPGR stockpile shown in magenta. The picture immediately below shows the currentconstruction progress (approximately 70% complete).

A 3D illustration of the tailings thickener (larger one in green) and concentrate thickener (smaller one in green), with the concentrate bagging plant shown in the background and the Phase 2 thickeners shown in magenta. The picture immediately below shows the currentconstruction progress (approximately 73% complete).

A 3D illustration of the reagent storage building, area, bagging plant and concentrate storage building, with Phase 2 shown in magenta. The picture immediately below shows the currentconstruction progress (approximately 30% complete).

Construction of the regrind mills at the concentrator plant is progressing rapidly.

Workers putting the finishing touches to the screening plant and surface ore conveyor system.

Ongoing construction of the concentrate bagging plant.

Workers installing a section for the two, 2,000-tonne silos at the backfill plant.

Watch a short, time-lapse video of the construction of the backfill plant’s 2,000-tonne silos:https://vimeo.com/485583080/a80283b88f

A 3D illustration of Kakula’s first phase, finished backfill plant, with the current construction (approximately 40% complete) and the initial 3.8 Mtpa concentrator plant in the background shown immediately below. The backfill plant will blend tailings from the concentrator with cement to produce paste backfill that will pumped back into the mine and used to help support mined-out areas. Approximately one half of the mine’s tailings will be sent back underground.

Watch a short, fly-over video of the construction of the backfill plant: https://vimeo.com/485579247/bc8297d722

A 3D illustration of Kakula’s bulk reclaim tip system that will be used to feed ore from Kakula’s surface stockpiles (and ore from the Kansoko Mine when Phase 2 operations begin) to the processing circuit. The current construction isshown immediately below (approximately 54% complete).

A 3D illustration of Kakula’sby-pass stockpile feed conveyor system. The current construction isshown immediately below (approximately 62% complete).

Electrician Abel Muianga installing a high-voltage electrical control box at the backfill plant.

Advanced, detailed discussions underway for the marketing of Kakula’s copper concentrates

Kamoa-Kakula is in advanced, detailed discussions with a number of parties with respect to the sale of its copper concentrates. Kakula is expected to produce an extremely high grade and clean copper concentrate (containing over 55% copper) that will be highly coveted by copper smelters around the world. Metallurgical test work indicates that the Kakula concentrates contain extremely low arsenic levels by world standards – approximately 0.01%.

Kamoa-Kakula preparing to be connected to the national power grid, providing clean, renewable 220-kV hydropower; first of six turbines at the refurbished Mwadingusha hydropower plant to be synchronized onto the national grid in December

Later this month, Kamoa-Kakula is expected to tie in the 35-kilometre, 220-kilovolt (kV) power line connecting theWestern Dispatch substation in Kolwezi to Kamoa-Kakula, and supply the project with reliable and clean hydro-generated electricity from the national grid.

Watch a short, fly-over video of the construction of the Kakula main electrical substation: https://vimeo.com/485582554/2b5d9b4741

Ivanhoe Mines Energy DRC is pleased to announce that the first of three turbines to be fully assembled this year at Mwadingusha hydropower plant went into final commissioning tests on November 26. The synchronization of this turbine onto the national electrical grid is scheduled for December 10, paving the way for the commissioning, in sequence, of the plant’s remaining five generating units, ensuring that Kamoa-Kakula’s power requirements of are met ahead of the commissioning of the concentrator plant. The fully-refurbished hydropower plant is expected to deliver approximately 72 megawatts of power to the national grid.

New water-pressure relief valves installed at the Mwadingusha hydropower plant.

In November, Mwadingusha’s water intake channel was filled in preparation for the commissioning and synchronization of the first of six refurbished turbines onto the national electrical grid.

Kamoa-Kakula’s COVID-19 prevention initiatives focused on risk mitigation

Kamoa-Kakula’s prevention measures remain strictly enforced. Rigorous testing, physical distancing, wearing face masks, frequent hand washing and contact-tracing measures are still in place to protect the safety and health of the workforce and community members.

The project has established a COVID-19 isolation facility at the Kamoa camp. Potential symptomatic patients are moved to this facility, where they will be isolated, tested and treated. Once patients have recovered and are deemed no longer infectious, they can return to work only after an additional quarantine period determined by the project’s medical staff.

As the pandemic evolves, the medical team at Kamoa-Kakula continues to review and update its risk mitigation protocols. The project’s preventative measures are at the highest international standards and should there be a case internally, the risk of spreading or cross-contamination is considered to be very low.

The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the DRC government (20%).

Electrician Simon Ndjamba Merve at Kakula’s new underground water-pumping station.

Olivier Kongo, one of the more than 6,300 employees and contractors building Kamoa-Kakula into the world’s next great copper mine.

Lunchtime at one of Kamoa-Kakula’s new dining facilities.

About Ivanhoe Mines

Ivanhoe Mines is a Canadian mining company focused on advancing its three principal joint-venture projects in Southern Africa: the development of major new, mechanized, underground mines at the Kamoa-Kakula copper discoveries in the DRC and at the Platreef palladium-platinum-nickel-copper-rhodium-gold discovery in South Africa; and the extensive redevelopment and upgrading of the historic Kipushi zinc-copper-germanium-silver mine, also in the DRC. Kamoa-Kakula is expected to begin producing copper in July 2021 and, through phased expansions, is positioned to become one of the world's largest copper producers. Kamoa-Kakula and Kipushi will be powered by clean, renewable hydro-generated electricity and will be among the world’s lowest greenhouse gas emitters per unit of metal produced. Ivanhoe also is exploring for new copper discoveries on its wholly-owned Western Foreland exploration licences in the DRC, near the Kamoa-Kakula Project.

Qualified Persons

Disclosures of a scientific or technical nature regarding development scenarios at the Kamoa-Kakula Project in this news release have been reviewed and approved by Steve Amos, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Amos is not considered independent under NI 43-101 as he is the Head of the Kamoa Project. Mr. Amos has verified the technical data disclosed in this news release.

Other disclosures of a scientific or technical nature regarding the stockpiles in this news release have been reviewed and approved by George Gilchrist, who is considered, by virtue of his education, experience and professional association, a Qualified Person under the terms of NI 43-101. Mr. Gilchrist is not considered independent under NI 43-101 as he is the Vice President, Resources of Ivanhoe Mines. Mr. Gilchrist has verified the other technical data disclosed in this news release.

The stockpile grade estimates contained in this release are based upon bulk ore sampling from earlier underground headings, and vertical channel sample profiles from recent development. Bulk ore sampling was done on each heading every second blast and three 5-kilogram samples were taken. Since the beginning of October 2020, channel sample profiles are the primary data informing the stockpile grade estimates. These are cut approximately 15 metres apart in 1-metre vertical increments across the full vertical exposure using a handheld grinder, with a 100-to-150-gram sample collected. The samples are pulverized at the project’s onsite laboratory and analyzed using a portable XRF (pXRF) instrument. Kamoa Copper has routinely analyzed its exploration drill core for copper using pXRF, in addition to analysis at a commercial laboratory using four acid digest and ICP-OES. This data has demonstrated that pXRF results can be relied upon for grade control and run-of-mine sampling.

Ivanhoe has prepared an independent, NI 43-101-compliant technical report for the Kamoa-Kakula Project, which is available on the company’s website and under the company’s SEDAR profile at www.sedar.com:

  • Kamoa-Kakula Integrated Development Plan 2020 dated October 13, 2020, prepared by OreWin Pty Ltd., China Nerin Engineering Co., Ltd., DRA Global, Epoch Resources, Golder Associates Africa, KGHM Cuprum R&D Centre Ltd., Outotec Oyj, Paterson and Cooke, Stantec Consulting International LLC, SRK Consulting Inc., and Wood plc.

The technical report includes relevant information regarding the assumptions, parameters and methods of the mineral resource estimates on the Kamoa-Kakula Project cited in this news release, as well as information regarding data verification, exploration procedures and other matters relevant to the scientific and technical disclosure contained in this news release.

Information contacts

Investors: Bill Trenaman +1.604.331.9834 / Media: Matthew Keevil +1.604.558.1034

Forward-looking statements

Certain statements in this release constitute “forward-looking statements” or “forward-looking information” within the meaning of applicable securities laws. Such statements and information involve known and unknown risks, uncertainties and other factors that may cause the actual results, performance or achievements of the company, its projects, or industry results, to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information. Such statements can be identified by the use of words such as “may”, “would”, “could”, “will”, “intend”, “expect”, “believe”, “plan”, “anticipate”, “estimate”, “scheduled”, “forecast”, “predict” and other similar terminology, or state that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. These statements reflect the company’s current expectations regarding future events, performance and results and speak only as of the date of this release.

Such statements include without limitation, the timing and results of: (i) statements regarding the Kamoa-Kakula Project is on track to have approximately three million tonnes of high-grade and medium-grade ore stockpiled on surface, containing more than 125,000 tonnes of copper, prior to the planned start of production in July 2021; (ii) statements regarding the expectation that the increased production of higher-grade ore to continue as additional mining crews begin working in the centre of the high-grade Kakula orebody; (iii) statements regarding the expectation that the project will achieve three key construction milestones in December – energizing the newly installed 220-kilovolt power line feeding Kamoa-Kakula with hydro-generated electricity from the national grid; synchronization of the first of six turbines at the refurbished Mwadingusha hydropower plant onto the national grid; and commissioning the main surface rock-handling, by-pass conveyor system that will enable the delivery of ore from the Kakula Mine directly to the concentrator plant stockpiles; (iv) statements regarding the expectation that Phase 2 of the project’s development when the Kakula concentrator processing capacity doubles to 7.6 Mtpa is to be commissioned in Q3 2022; (v) statements regarding Kakula is projected to be the world’s highest-grade major copper mine, with an initial mining rate of 3.8 Mtpa at an estimated average feed grade of more than 6.0% copper over the first five years of operation; (vi) statements regarding Phases 1 and 2 combined are forecast to produce approximately 400,000 tonnes of copper per year; statements regarding based on independent benchmarking, the project’s phased expansion scenario to 19 Mtpa would position Kamoa-Kakula as the world’s second largest copper mining complex, with peak annual copper production of more than 800,000 tonnes; (vii) statements regarding Kamoa-Kakula will be among the world's lowest greenhouse gas emitters per unit of copper produced; (viii) statements regarding approximately one half of the mine’s tailings will be sent back underground; (ix) statements regarding Kakula is expected to produce an extremely high grade and clean copper concentrate (containing over 55% copper and extremely low arsenic levels by world standards – approximately 0.01%) that will be highly coveted by copper smelters around the world; and, (x) statements regarding the fully-refurbished Mwadingusha hydropower plant is expected to deliver approximately 72 megawatts of power to the national grid.

As well, all of the results of the Kakula definitive feasibility study, the Kakula-Kansoko pre-feasibility study and the Kamoa-Kakula preliminary economic assessment, constitute forward-looking statements or information, and include future estimates of internal rates of return, net present value, future production, estimates of cash cost, proposed mining plans and methods, mine life estimates, cash flow forecasts, metal recoveries, estimates of capital and operating costs and the size and timing of phased development of the projects. Furthermore, with respect to this specific forward-looking information concerning the development of the Kamoa-Kakula Project, the company has based its assumptions and analysis on certain factors that are inherently uncertain. Uncertainties include: (i) the adequacy of infrastructure; (ii) geological characteristics; (iii) metallurgical characteristics of the mineralization; (iv) the ability to develop adequate processing capacity; (v) the price of copper; (vi) the availability of equipment and facilities necessary to complete development; (vii) the cost of consumables and mining and processing equipment; (viii) unforeseen technological and engineering problems; (ix) accidents or acts of sabotage or terrorism; (x) currency fluctuations; (xi) changes in regulations; (xii) the compliance by joint venture partners with terms of agreements; (xiii) the availability and productivity of skilled labour; (xiv) the regulation of the mining industry by various governmental agencies; (xv) the ability to raise sufficient capital to develop such projects; (xiv) changes in project scope or design; and (xv) political factors.

Forward-looking statements and information involve significant risks and uncertainties, should not be read as guarantees of future performance or results and will not necessarily be accurate indicators of whether or not such results will be achieved. A number of factors could cause actual results to differ materially from the results discussed in the forward-looking statements or information, including, but not limited to, the factors discussed below and under “Risk Factors”, and elsewhere in this release, as well as unexpected changes in laws, rules or regulations, or their enforcement by applicable authorities; the failure of parties to contracts with the company to perform as agreed; social or labour unrest; changes in commodity prices; and the failure of exploration programs or studies to deliver anticipated results or results that would justify and support continued exploration, studies, development or operations.

lthough the forward-looking statements contained in this release are based upon what management of the company believes are reasonable assumptions, the company cannot assure investors that actual results will be consistent with these forward-looking statements. These forward-looking statements are made as of the date of this release and are expressly qualified in their entirety by this cautionary statement. Subject to applicable securities laws, the company does not assume any obligation to update or revise the forward-looking statements contained herein to reflect events or circumstances occurring after the date of this release.

The company’s actual results could differ materially from those anticipated in these forward-looking statements as a result of the factors set forth below in the “Risk Factors” section in the company’s Q3 2020 MD&A and its current annual information form.

剛果民主共和國科盧韋齊 — 艾芬豪礦業 (TSX: IVN; OTCQX:IVPAF) 聯席董事長羅伯特·弗里蘭德 (Robert Friedland) 與孫玉峰 (Miles Sun) 今天欣然宣布,其位于剛果民主共和國 (以下簡稱“剛果(金)”) 的卡莫阿-卡庫拉銅礦項目的地下開發持續推進,11月份在卡庫拉和卡索科礦山共采掘了250,000噸礦石,銅品位4.85%,礦石量相比10月份高出29%,月度銅品位從4.01%提升至4.85%。

項目的投產前地表堆場,目前已儲備了約125萬噸高品位和中品位礦石,銅品位約3.75%。礦堆的含銅量于11月份提升至約12,100噸 — 相比10月份高出55%,累計含銅量達46,700噸以上 (目前的銅價約每噸銅7,460美元)。項目將按計劃于2021年7月實現投產前,在地表堆場儲備約300萬噸高品位和中品位礦石,含有超過125,000噸銅金屬。

弗里蘭德先生和孫先生表示,采掘班組于11月份共掘進2,163米,與項目的月度最高記錄僅僅相差10米??◣炖媳眱蓷l主要運輸通道已于11月初完成貫通,實現了項目的一個重要里程碑,并到達高品位的礦床中心,該礦段的銅品位約8%以上 (見圖1、2和3 )。根據標準的安全預防措施,貫通工程在過去幾天只是從一端推進,但對整體的掘進距離影響不大。

貫通工程使卡庫拉的采掘班組可以擴大礦床中心的開拓巷道至7米寬x7米高 (約23尺寬x23尺高),利用礦段厚大且銅品位極高的優勢,大大提升采掘的礦石量。

11月份的的地下開發持續推進,至今已完成超過26.8公里,超越既定目標約9.0公里。 11月份的月度地下開拓工程共掘進2,163米,其中包含在卡庫拉礦山掘進的1,840米和在卡索科礦山掘進的323米??ㄋ骺频V山位于卡莫阿礦區范圍內,距離卡庫拉礦山以北約10公里處。

卡莫阿銅業首席執行官馬克·法倫(Mark Farren) 說﹕“11月份的礦山開發進展理想??◣炖饕\輸通道已完成連接,為南北兩面的斜坡道(相距約4公里)提供運輸通道并改善通風情況。此外,我們還創下了采掘礦石量的紀錄,且銅品位顯著增加。隨著更多采掘班組在卡庫拉礦床中心的高品位礦段開始作業,我們預計這個增長勢頭將會持續下去。11月份,卡索科礦山錄得的銅品位急劇上升,主要是由于接觸到的富銅粉砂巖層不斷加厚?!?/p>

法倫先生補充說﹕“我們預計將于本月實現三項關鍵的建設里程碑,包括﹕新安裝的220千伏電力線將會通電,從國家電網為卡莫阿-卡庫拉項目提供水電能源;翻新后的 Mwadingusha 水電廠6臺渦輪機中的第1臺將與國家電網同步;以及主要的地表巖石分支輸送系統將開始運行,直接從卡庫拉礦山運送礦石至選礦廠的堆場?!?/p>

目前,卡庫拉的地下采掘班組正專注于礦床中心高品位分層充填采礦區的開發工作。為了能在這些高品位的分層充填礦段展開采礦作業,必須要在低、中和高品位礦段都進行開發工作,這一設計也是為了配合計劃于明年開始運行的選礦廠。這將使采掘班組可從卡庫拉地下直接運送大量的高品位礦石到選礦廠。

卡索科礦山大多數的地下開拓工程在中品位礦段進行,但采掘班組于11月底到達了礦床首個高品位礦段,并于月底采掘了2,100噸高品位礦石,銅品位達6.66%。 11月份在卡索科采掘的高品位和中品位礦石合共約33,000噸,平均銅品位為3.87%。由于接觸到的粉砂巖層不斷加厚,因此11月份在卡索科錄得的銅品位急劇上升。粉砂巖對于卡莫阿-卡庫拉的銅礦化形成有著重大的影響。

卡索科由訓練有素的采礦隊伍進行開發,開采的礦石將會補足項目在進行第二序列開發時,卡庫拉選礦廠擴大至760萬噸/年的產能需求,預計于2022年第三季度實現投產。

卡庫拉礦山計劃于2021年7月實現首批銅生產,預期將會成為全球品位最高的大型銅礦,初始年處理礦量為380萬噸,預計投產后前5年的平均給礦銅品位達6.0%以上。第一和第二序列總共每年將會生產約400,000噸的銅金屬。根據獨立的研究機構排名,一旦項目擴產至1,900萬噸/年,卡莫阿-卡庫拉將成為全世界第二大銅礦山,年度最高銅產量將超過800,000噸。

加拿大密西沙加的Hatch Ltd.對于卡莫阿-卡庫拉的溫室氣體強度指標進行了獨立審核,確定項目將會成為全球每單位銅溫室氣體排放量最低的礦山之一。

施工中的卡庫拉礦山和第一座380萬噸/年選礦廠的簡短航拍視頻,可通過此鏈接進行觀看﹕https://vimeo.com/485580022/276d6411df

從左至右﹕生產經理 Magloire Kashiba、業務主管 Jan Strydom、艾芬豪礦業總裁兼首席財務官瑪娜·科洛特 (Marna Cloete) 和部門經理 Pontien Kalala 共同慶??◣炖闹饕ǖ烙?1月初完成貫通,為南北兩面的斜坡道提供運輸通道并改善通風情況。

卡莫阿-卡庫拉的地表施工團隊,截至11月份達到500萬個零失時工傷小時的紀錄。

工作人員在卡庫拉高品位礦床中心鉆探7米寬x7米高的開拓巷道。

11月份開采的礦石量較10月份高出29%,月度銅品位從4.01%提升至4.85%;投產前地表礦堆目前已儲備礦石量約125萬噸,銅品位3.75%

采掘班組于11月份已在卡庫拉和卡索科礦山開采及運送約250,000噸礦石到地表礦堆,銅品位4.85%。項目的投產前高品位和中品位礦堆已儲備礦石量約125萬噸,銅品位約3.75%。另外,622,000噸較低品位的礦石也運送到地表的礦堆。

11月份開采的礦石量較10月份 (194,000噸,銅品位3.47%) 高出約29%,較9月份 (132,000噸,銅品位3.31%) 則高出約89%。隨著更多采掘班組在卡庫拉和卡索科礦山的高品位礦段開始作業,項目將繼續大大提升地表堆場的礦石量,且礦石品位將會有所增加。

圖表1﹕2020年5月至2020年11月期間卡庫拉和卡索科礦山的投產前礦堆累計儲備的礦石量和品位。

圖表2﹕2020年5月至2020年11月期間卡庫拉和卡索科礦山的投產前礦堆含銅量增長。

圖表3﹕2021年7月第一序列投產前,卡庫拉和卡索科礦山的投產前礦堆累計含銅量增長估算。虛線是以2020年預可行性研究為基礎而作出的預測。

在卡庫拉礦山北部開采的礦石經由輸送系統,運送到地表的混合礦堆?;旌系V堆目前已儲備礦石量約763,000噸,銅品位約3.93%。

此外,項目還有兩個額外的投產前礦堆,分別位于卡庫拉南面斜坡道 (約107,000 噸高品位礦石,銅品位6.11%以及224,000噸中品位礦石,銅品位2.64%) 和卡索科斜坡道 (約2,100 噸高品位礦石,銅品位6.66%以及151,000噸中品位礦石,銅品位2.82%)。

卡庫拉北面斜坡道的主要投產前礦堆?;旌系V堆目前已儲備礦石量約763,000噸,銅品位3.93%。

卡庫拉南面斜坡道的礦石堆場目前已儲備約107,000噸高品位礦石,銅品位6.11%以及224,000噸中品位礦石,銅品位2.64%。

卡索科斜坡道的礦石堆場目前已儲備153,000噸礦石,銅品位2.82%,其中包括首批2,100噸高品位礦石,銅品位達6.66%。

圖1﹕卡庫拉礦床總長度13.3公里,覆蓋在曼哈頓島南部(如下圖),可見其規模之大。

圖2﹕卡庫拉礦床總長度13.3公里,覆蓋在巴黎地圖上(如下圖),可見礦床和地下作業的規模之大。

圖3:截至2020年11月27日在卡庫拉礦山已完成的地下開拓工程 (黑色)。

年處理礦量380萬噸初始選礦廠和其他地表基礎設施的施工快速推進;第二座年處理礦量380萬噸選礦廠的土方工程和土木工程已開始施工,并已簽訂項目設計采購與施工管理總承包合同(以下簡稱“EPCM”)。

卡莫阿-卡庫拉第一序列的年處理礦量380萬噸開采選礦作業 (包括礦山基礎設施、選礦廠和地表基礎設施) 整體施工進度理想,目前已完成約63%,上月則完成了58%。項目第一座380萬噸/年選礦廠和相關基礎設施的整體施工正在快速推進,目前已完成約35%,上月則完成了28%。選礦廠預計于2021年第二季度完工,并計劃于2021年7月實現首批銅精礦生產。

初始選礦廠的土木工程已完成了90%以上,至今已灌入約28,000立方米的混凝土。所有主要廠房區域已移交給結構、機械、管道和鈑金(以下簡稱“SMPP”)承包商繼續施工。

超過2,000輛卡車的設備 (包括最后的主要設備 — 兩臺80兆伏安/220千伏的變壓器) 已抵達礦場。變壓器已放到卡庫拉變電站內的指定位置,項目多個變電站的施工進度理想。

所有鋼結構以及大部分的板金和管道已運達現場。管道的安裝工程已經展開,并已開始安裝電纜架和電纜。

目前,超過3,000噸 (總共5,700噸) 的鋼結構已完成安裝。選礦廠所有廠房區域已經開始進行SMPP的搭建和安裝且進展順利。選礦、浮選和濃密區的電器安裝也正在進行中。

最近的重點工程包括在試劑倉庫和精礦倉庫安裝頂板,安裝完成后,現場的制造工程將不會受到雨天的影響。

卡庫拉第一序列回填廠的鋼架安裝進展理想,大部分的外部結構已經完成,其中高架起重機已完成安裝。兩座2,000噸的水泥儲倉的安裝正進行中。鋼結構的安裝計劃于2021年初完工。

回填廠將選礦廠的尾礦與水泥混合制造回填漿?;靥顫{將會泵回礦山用作填充采空區。礦山約一半的尾礦將被泵送回地下,大大減少地表的尾礦量。

尾礦壩的施工進度理想,將于規劃時間之前完工。三條尾礦管道和尾礦回水管的安裝也快將完成。

目前已為第二座380萬噸/年選礦廠的長周期設備下訂單,開始第二序列的開發工作,并已簽訂土方工程合同,開始進行土木工程和清除灌木工作,同時已經與北京的中國恩菲工程公司簽訂EPCM的合同。

卡莫阿銅業首席執行官馬克·法倫 (左) 與恩菲工程國際業務部總經理黃穎生(右)簽訂卡莫阿-卡庫拉第二序列選礦廠的EPCM合同。

圖片上半部分為已建成的第一座380萬噸/年選礦廠的三維鳥瞰圖,下半部分顯示了當前的施工進度 (已完成約41%)。

圖片上半部分為第一座380萬噸/年選礦廠已建成的球磨機廠區的三維示意圖,規劃中用于第二座選礦廠的另外兩座球磨機則以紫色顯示。圖片下半部分顯示了當前的施工進度 (已完成約59%)。

圖片上半部分為卡庫拉380萬噸/年初始選礦廠的三維示意圖,規劃中的第二座380萬噸/年選礦廠則以紫色顯示。圖片下半部分顯示了當前的施工進度 (已完成約48%)。

圖片上半部分為首個高壓輥磨機礦倉的三維示意圖,規劃中的第二個高壓輥磨機礦倉則以紫色顯示。圖片下半部分顯示了當前的施工進度 (已完成約70%)。

圖片上半部分為尾礦濃密機 (大— 以綠色顯示) 和精礦濃密機 (小— 以綠色顯示) 的三維示意圖,背景為精礦裝袋廠房,規劃中的第二組濃密機則以紫色顯示。圖片下半部分顯示了當前的施工進度 (已完成約73%)。

圖片上半部分為試劑倉庫、裝袋廠房和精礦倉庫的三維示意圖,第二序列則以紫色顯示。圖片下半部分顯示了當前的施工進度 (已完成約30%)。

選礦廠研磨機的施工正在快速推進。

工作人員在篩選廠和地表礦石輸送系統完成最后的細節工作。

施工中的精礦袋裝廠房。

工作人員在回填廠兩座2,000噸的儲倉安裝組件。

關于建造回填廠的2,000噸儲倉的簡短快放視頻,可通過此鏈接進行觀看:https://vimeo.com/485583080/a80283b88f

圖片上半部分為已完工的卡庫拉第一序列回填廠的三維示意圖,下半部分顯示了當前的施工進度 (已完成約40%),背景為年處理礦量380萬噸的初始選礦廠?;靥顝S將選礦廠的尾礦與水泥混合制造回填漿?;靥顫{將會泵回礦山用作填充采空區。礦山約一半的尾礦將被泵送回地下。

關于回填廠施工的簡短航拍視頻,可通過此鏈接進行觀看:https://vimeo.com/485579247/bc8297d722

圖片上半部分為卡庫拉大型回收卸料系統的三維示意圖,將從卡庫拉地表礦堆 (于第二序列作業開始后也從卡索科礦山) 運送礦石供給選礦廠。圖片下半部分顯示了當前的施工進度 (已完成約54%)。

圖片上半部分為卡庫拉分支礦堆輸送系統的三維示意圖,下半部分顯示了當前的施工進度 (已完成約62%)。

電工Abel Muianga在回填廠安裝高壓電氣控制箱。

關于卡庫拉銅精礦銷售方案的深入詳細討論正在進行中

目前,卡莫阿-卡庫拉正與多方就銅精礦的銷售進行深入和詳細討論??◣炖瓕a極高品位的清潔銅精礦 (含銅量達55%以上),將會是世界各地銅冶煉廠渴求的高質量產品。冶金測試結果顯示,相較全球標準,卡庫拉精礦的含砷量極低,約為0.01%。

卡莫阿-卡庫拉作好準備與國家電網的電力線相連接,為項目提供清潔、可再生的220千伏水電能源;翻新后的Mwadingusha水電廠6臺渦輪機中的第1臺將與國家電網同步

卡莫阿-卡庫拉預計將于本月晚些時候,與位于科盧韋齊的西部調度 (Western Dispatch) 變電站通過一條35公里長的220千伏電力線相連通,從國家電網為項目提供可靠和清潔的水電能源。

關于卡庫拉主要變電站施工的簡短航拍視頻,可通過此鏈接進行觀看:https://vimeo.com/485582554/2b5d9b4741

艾芬豪礦業剛果(金)能源公司 (Ivanhoe Mines Energy DRC) 公布,Mwadingusha水電站3臺渦輪機的第一臺已于11月26日進行最終調試,并將于今年內全面組裝。這臺渦輪機將于12月10日與國家電網同步,為水電廠余下5臺發電機日后的調試做準備,確???卡庫拉在選礦廠投產前獲得充足的電能供應。全面翻新后的水電廠預計將向國家電網提供72 兆瓦的電力。

Mwadingusha水電廠已安裝新的水壓泄壓閥。

Mwadingusha于11月份注水入引水渠,為6臺翻新的渦輪機的第一臺進行調試及與國家電網同步作好準備。

卡莫阿-卡庫拉項目的COVID-19防疫措施側重于降低風險

卡莫阿-卡庫拉礦山繼續實施防疫措施如嚴格測試、保持距離、配戴口罩、經常洗手及追蹤調查接觸者等,以保護員工和社區成員的安全和健康。

目前已在卡莫阿項目營地設有COVID-19隔離設施。任何疑似或出現病癥的人員都將會安排到該設施,進行隔離、檢測和治療?;颊呖祻颓也辉倬邆魅拘院?,必須在項目醫務人員規定的額外隔離觀察期結束后,才可返回工作崗位。

隨著疫情的變化,卡莫阿-卡庫拉的醫療隊伍將繼續不斷審核和更新其疫情防控方案。項目的防疫措施符合國際最高標準,內部出現感染病例,傳播或交叉感染的風險也非常低。

卡莫阿-卡庫拉銅礦項目是艾芬豪礦業 (占股39.6%)、紫金礦業集團 (占股39.6%)、晶河全球 (占股0.8%) 及剛果(金)政府 (占股20%) 的合資項目。

電工Simon Ndjamba Merve在卡庫拉新的地下水泵站。

Olivier Kongo與項目6,300多名員工和承包商,攜手將卡莫阿-卡庫拉打造成為世界下一個大型銅礦。

在卡莫阿-卡庫拉新食堂的午餐時間。

關于艾芬豪礦業

艾芬豪礦業是一家加拿大的礦業公司,目前正推進旗下位于南部非洲的三大合資企業項目﹕位于剛果(金)的卡莫阿-卡庫拉銅礦和位于南非的普拉特瑞夫 (Platreef) 鈀-鉑-鎳-銅-銠-金礦的大型機械化地下礦山開發工程,以及同樣位于剛果(金)、久負盛名的基普什 (Kipushi) 鋅-銅-鍺-銀礦的大型重建和改善工程???卡庫拉預計將于2021年7月實現銅生產,并分階段進行擴建,預計將會成為全球最大規模的銅生產商之一???卡庫拉和基普什將使用清潔、可再生的水電,并將成為全球每單位金屬溫室氣體排放量最低的礦山之一。同時,艾芬豪正在剛果(金)境內其全資擁有、毗鄰卡莫阿-卡庫拉項目的西部前沿 (Western Foreland) 勘探許可區內尋找新的銅礦資源。

合資格人士

本新聞稿中關于卡莫阿-卡庫拉項目的科學或技術性披露已經由史蒂夫·阿莫斯 (Steve Amos) 審查和批準,他憑借其教育、經驗和專業協會會籍被認為是NI 43-101 標準下的合資格人士。由于阿莫斯先生是卡莫阿項目的負責人,因此他并不符合NI 43-101 對獨立人士的界定。阿莫斯先生已核實本新聞稿所披露的技術數據。

本新聞稿中關于礦堆的其它科學或技術性披露已經由喬治·吉爾克里斯特 (George Gilchrist) 審查和批準,他憑借其教育、經驗和專業協會會籍被認為是NI 43-101 條款下的合資格人士。由于吉爾克里斯特先生是艾芬豪礦業資源部副總裁,因此他并不符合NI 43-101 對獨立人士的界定。吉爾克里斯特先生已核實本新聞稿所披露的其它技術數據。

本新聞稿所載的礦堆品位估算值是基于早前從地下巷道的大塊礦石取樣以及從最近開發的垂直剖面刻槽取樣。每個巷道進行第二次爆破時取樣,并收集3個5公斤重的樣品。從2020年10月起使用刻槽取樣的樣品作為礦堆品位估算的主要數據,大約每15米在整個垂直剖面上使用手持式研磨機按1米垂直增量進行采樣,收集100-150克重的樣品。樣品在項目現場實驗室粉碎后,使用便攜式XRF (pXRF) 儀器進行分析。除了在商業實驗室利用4種酸分解液和ICP-OES進行分析之外,卡莫阿銅業也經常使用pXRF分析其鉆孔巖芯中的銅含量。該數據表明,pXRF結果可用于品位控制和采礦井取樣。

艾芬豪已經為卡莫阿-卡庫拉項目編制了一份符合NI 43-101 標準的獨立技術報告,該報告可在艾芬豪網站以及SEDAR 網站上的艾芬豪頁面獲得,網址為www.sedar.com

  • 2020年10月13日發布的2020年卡莫阿-卡庫拉綜合開發方案,由OreWin Pty Ltd.、中國瑞林工程技術有限公司、DRA Global、Epoch Resources、Golder Associates Africa、KGHM Cuprum R&D Centre Ltd. 、Outotec Oyj、Paterson and Cooke、Stantec Consulting International LLC、SRK Consulting Inc.以及Wood plc編制。

技術報告包括本新聞稿中引用的卡莫阿-卡庫拉項目的礦產資源估算的假設、參數和方法等信息,以及本新聞稿中關于科學和技術性披露的數據驗證、勘探程序和其他事項的信息。

聯系方式

投資者﹕Bill Trenaman +1.604.331.9834 / 媒體﹕Matthew Keevil +1.604.558.1034

前瞻性陳述
本新聞稿載有的某些陳述可能構成適用于證券法所定義的“前瞻性陳述”或“前瞻性信息”。該等陳述及信息涉及已知和未知的風險、不明朗因素和其他因素,可能導致本公司的實際業績、表現或成就、其項目或行業的業績,與前瞻性陳述或信息所表達或暗示的任何未來業績、表現或成就產生重大差異。該等陳述可通過文中使用“可能”、“將會”、“會”、“將要”、“打算”、“預期”、“相信”、“計劃”、“預計”、“估計”、 “安排”、“預測”、“預言”及其他類似用語,或者聲明“可能”、“會”、“將會”、“可能會”或“將要”采取、發生或實現某些行動、事件或結果進行識別。這些陳述僅反映本公司于本新聞稿發布當日對于未來事件、表現和業績的當前預期。

該等陳述包括但不限于下列事項的時間點和結果﹕(i) 關于卡莫阿-卡庫拉項目將按計劃于2021年7月實現投產前,在地表堆場儲備約300萬噸高品位和中品位礦石,含有超過125,000噸銅金屬的陳述;(ii) 關于隨著更多采掘班組在卡庫拉礦床中心的高品位礦段開始作業,預計增長勢頭將會持續的陳述;(iii)關于項目預計將于12月實現三項關鍵的建設里程碑,包括﹕新安裝的220千伏電力線將會通電,從國家電網為卡莫阿-卡庫拉項目提供水電能源;翻新后的Mwadingusha 水電廠的6臺渦輪機中第1臺與國家電網同步;以及主要的地表巖石處理分支輸送系統開始運行,直接從卡庫拉礦山運送礦石至選礦廠堆場的陳述;(iv) 關于在第二序列開發時,卡庫拉選礦廠擴大至760萬噸/年的產能需求,預計于2022年第三季度實現投產的陳述;(v) 關于卡庫拉預期將會成為全球品位最高的大型銅礦,初始年處理礦量為380萬噸,預計投產后前5年的平均給礦銅品位達6.0%以上的陳述;(vi) 關于第一和第二序列總共每年將會生產約400,000噸的銅金屬;根據獨立的研究機構排名,一旦項目擴產至1,900萬噸/年,卡莫阿-卡庫拉將成為全世界第二大銅礦山,年度最高銅產量將超過800,000噸的陳述;(vii)關于卡莫阿-卡庫拉項目將會成為全球每單位銅的溫室氣體排放量最低礦山之一的陳述;(viii) 關于礦山約一半的尾礦將被泵送回地下的陳述;(ix)關于卡庫拉將會生產極高品位的清潔銅精礦(含銅量達55%以上,相較全球標準含砷量極低,約為0.01%),將會是世界各地銅冶煉廠渴求的高質量產品的陳述;以及(x) 關于Mwadingusha水電廠全面翻新后預計將向國家電網提供72 兆瓦電力的陳述。

此外,卡庫拉最終可行性研究、卡庫拉-卡索科預可行性研究及卡莫阿-卡庫拉項目初步經濟評估的所有結果,構成了前瞻性陳述或信息,并包括內部收益率的未來估算、凈現值,未來產量、現金成本估算、建議采礦方案和方法、礦山壽命估計、現金流預測、金屬回收率、資本和運營成本估算,以及項目分期開發的規模和時間點。另外,對于與卡莫阿-卡庫拉項目開發有關的特定前瞻性信息,公司是基于某些不確定因素而作出假設和分析。不確定因素包括:(i) 基礎設施的充足性;(ii) 地質特征;(iii) 礦化的冶金特征;(iv) 發展充足選礦產能的能力;(v) 銅價格;(vi) 完成開發所需的設備和設施的可用性;(vii) 消耗品和采礦及選礦設備的費用;(viii) 不可預見的技術和工程問題;(ix) 事故或破壞或恐怖主義行為;(x) 貨幣波動; (xi) 法例修訂;(xii) 合資伙伴對協議條款的遵守情況;(xiii) 熟練勞工的人手和生產率;(xiv) 各政府機構對礦業的監管;(xv) 籌集足夠資金以發展該等項目的能力;(xiv) 項目范圍或設計更變;以及(xv) 政治因素。

前瞻性陳述及信息涉及重大風險和不確定性,故不應被視為對未來表現或業績的保證,并且不能準確地指示能否達到該等業績。許多因素可能導致實際業績與前瞻性陳述或信息所討論的業績有重大差異,包括但不限于“風險因素”以及本新聞稿其他部分所指的因素,以及有關部門實施的法律、法規或規章或其不可預見的變化;與本公司簽訂合約的各方沒有根據協議履行合約;社會或勞資糾紛;商品價格的變動;以及勘探計劃或研究未能達到預期結果或未能產生足以證明和支持繼續勘探、研究、開發或運營的結果。

雖然本新聞稿載有的前瞻性陳述是基于本公司管理層認為合理的假設而作出,但本公司不能向投資者保證實際業績會與前瞻性陳述的預期一致。這些前瞻性陳述僅是截至本新聞稿發布當日作出,而且受本警戒性聲明明確限制。根據相應的證券法,本公司并無義務更新或修改任何前瞻性陳述以反映本新聞稿發布當日后所發生的事件或情況。

由于公司在2020年第三季度管理層討論和分析和當前年度報告中“風險因素”部分所列的因素,公司的實際業績可能與這些前瞻性陳述中預期的業績有重大差異。

Download in PDF Format

Subscribe to our Email List

软萌小仙自慰喷白浆,国产肥熟女视频一区二区,无码刺激性A片,国产亚洲日韩在线播放不卡
老子影院 啵乐官方网页 附近的妇女 我的美女房东免费观看 72种性姿势真人示范 武媚娘免费完整版观看 国产在热线精品视频99 蝶恋直播app 青青河边草免费观看 天堂资源最新版 亚洲五月综合自拍区 一本到高清在线视频观看 家庭教师动漫免费观看 mm131 尖湿锐尤早期图片 姐姐的朋友 2020国自产拍精品网站 佛山 250qq 身为人母在线观看免费 年轻母亲2 4hc44四虎www网址2 手机短片 久草原精品资源视频 水咲ローラ 小草免费观看在线播放 同性男在啪的动漫网站 closeup毛茸茸pics大全 都市仙尊洛尘全集目录 给人一种阳光的头像 日本laurenphilips 欧美顶级情欲片 新翁熄粗大 毛泽东思想和中国特色社会主义理论体系概论 bt天堂www 717电影网 热热色 BT蚂蚁磁力天堂 将军夫人又跑了 一品道门免费视频日本 天堂俺去俺来也www色官网 阿娇与冠希13分钟无删减视频 川娇网 如此可爱的我们电视剧免费观看 小鬼翔太 男人a天堂2814 葡萄视频 拍摄指南 武媚娘免费完整版观看 受委屈离家出走被惩罚 磁力天堂torrent 久久这里只精品免费6 哔咔漫画app下载 附近人妇女 三级片在线观看 2020给个网站好人有好报 小鬼翔太 亚洲 无码 在线 专区 西游记86版全集 2020抖音最火网名 佛山市地图 亚洲香蕉网久久综合影院 4399电影在线观看 色狗电影网 2019最新无码国产在线视频 日日拍夜夜嗷嗷叫 芭乐视频app下载官方 神都猛虎岳风小说免费 2020抖音最火网名 快猫下载 抖阴app 柠檬tv 真人做人试看120分钟 幸福花园 菠萝菠萝蜜手机网 无尽长廊污的 薰衣草免费观看全集在线 天天影视综合网网综合 bt天堂在线 闺蜜2在线观看完整版中字 老子影院 250qq 免费黄色片 mdyd-754 磁力天堂 青青河边草免费观看 汤姆高清影院 无尽长廊 最新在线伦费观看中文 郑州桑拿 任你躁在线精品免费 身份证号码游戏注册用 欧洲攻略视频免费观看 啵乐app 折腰蓬莱客肉肉 五色天 四虎最新2019入口地址 67194成l人在线观看线路 将夜免费神马影院影视 秋葵视频丝瓜视频 网易黄页 情欲满载 日本一区二区 至高指令未删减在线 私人拍摄 中文字幕亚洲无线码a pin6 莎翁情史 4399看片 八佰电影免费高清完整版在线观看 6080yy 哔咔漫画 菠萝蜜官网 土豆app社交 玖玖热 韩国三级年轻小的胰子 给人一种阳光的头像 老湿免费48福利体检区 治早迣简单快速的方法 nana高清在线观看 虫爱少女 艳女伦交 叶凡秋沐橙 国产野外无码理论片在线观看 诸天万界推倒女主角 秋霞电影院yy2933 快活视频 月光影视在线观看 被窝里的公憩第26章 精品国产自在天天线2019 亚洲欧洲自拍图片专区 yy11111光电影院手机版 国产毛片农村妇女系列bd版 短文集合 蝶恋 偷偷藏不住新婚番外 柠檬tv 《禁止的爱》在线播放 免费99精品国产自在现线 人妻无奈迎合粗大 将军夫人又跑了了全文免费阅读 5个小妙招巧治口腔溃疡 免费精品国自产网站 狗带tv首页 破外女出血在线视频高清在线 s8视频 亚洲色tu 国内少妇高清露脸精品视频 黃色大片完整版免費 2020必看电影排行榜前十名 天堂资源最新版 nana在线观看高清视频 人猿泰山h 欧美日韩亚洲中字二区 酒色世界 猪蜜蜜电视剧大全 一本大道香蕉中文在线视频 jizzjizz 国产第一页 s8视频 凌依然易谨离小说阅读全文免费阅读 free性欧美极度另类 2020抖音最火网名 洛尘最新更新章节笔趣阁 绝世高手陈扬最新更新章节 一本大道香蕉中文在线视频 欲望妹妹 秋霞电影网午夜鲁丝片无码 神之一手 西西gogo高清大胆专业 单身网 污动漫 同房交换4p好爽 中文字幕大香视频蕉免费 免费99精品国产自在现线 致命的你漫画在线观看全集免费 中文字字幕在线中文乱码不卡 青青河边草免费观看2019 老司机67194精品线观看 诸天万界推倒女主角 妈妈的朋友5 亚洲中文字幕永久在线 中国黄页大全 新婚娇妻宠上瘾 avtt 欧美色视频日本片免费 年轻的母亲在线观看 北地胭脂 幸福花园 最好看的2019中文字幕 铃木秀一 都市重生修仙洛尘最新 身份证号码游戏注册用 国产原创剧情麻豆在线 国产短视频精品区 韩国三级年轻小的胰子 佛山交警信息服务网 天堂最新版 治早迣简单快速的方法 穿越民国泡尽美人 菠萝菠萝蜜在线视频在线播放 qimi 草柳 汤姆叔叔的小屋 哔咔漫画app下载 啵乐网页 手机黄页 汤姆叔叔的小屋主要内容 99久久免费只有精品 快猫下载 最大胆人体艺术图片 任你躁在线精品免费 偷偷藏不住 凌依然易谨离全文小说 国产野外无码理论片在线观看 男同视频 日本道专区无码中文字幕 翁熄系列36章 妈妈的朋友7 菠萝视频香蕉视频 成事在人电影免费观看 娇艳都市未删减小说 中国大黄页 川娇网 磁力天堂 巳怎么读 都市仙尊洛尘最新章节更新 yy4480 黑米影院 人间情缘 婷婷五月天 磁力天堂在线 穿成三个男配大佬的解药 62fan 磁力天堂torrent 日本高级按摩人妻无码 千人斩官网 秋霞电影院yy2933 日本道专区无码中文字幕 天天爱去 超级全能学生 热热色 保险女王 偷偷藏不住 67194线路1(点击进入) 台湾自拍偷区亚洲综合 柠檬tv 穿越民国泡尽美人 香蕉伊思人在钱 香港肉丸子事件是什么意思 杂烩大乱炖目录 一本到高清在线视频观看 蝴蝶论坛 陈扬绝世高手今日更新 日本三级片电影 啵乐官网入口 purnhurb官网是什么 都市洛尘最新章节更新 木瓜网 铃木秀一 五色天 久青草视频免费视频 洛尘重生之都市仙尊最新章节 老扒夜夜春宵第二部的 日本高清视频在线一本视频 微拍网 狼人香蕉香蕉在线28 - 百度 来吧综合 2020必看电影排行榜前十名 啵乐app下载 无尽长廊 第一精品福利导福航 超级女婿赵旭李晴晴全文免费阅读 最新国自产拍在线播放 女阁 将军夫人又跑了全文免费阅读全文 2828 奇优 香蕉一本大道中文在线 糯美子 都市仙尊洛尘全集目录 噜噜射 国产肥熟女视频一区二区 欧美色视频日本片免费 秋葵视频app下载 宅男的天堂 韩国三级年轻小的胰子 三级片在线观看 年轻的小峓子4中字 无码精品 日韩专区 白洁被双飞 avtt id002 欧美黄色片 男同视频 独家试爱 超级全能学生杀猪刀 琅琊榜在线观看免费观看 樱桃红在线看免费观看视频 女主重生变娇媚体制 chengren 爸爸的朋友 年轻的小婊3中文字 宅男的天堂 年轻母亲4 身为人母免费播放电影 锦衣天下电视剧西瓜免费 老奶奶rap 大伊香蕉精品视频在线 老湿免费48福利体检区 4399看片 精品国产自在天天线2019 台湾老 二次元超污没有衣服无遮无挡 伊在香蕉国产在线视频 土豆app社交 顾轻舟司少帅免费阅读最新章节 磁力天堂樱桃bt 春光乍泄高清图 琉璃免费观看电视剧全集54 365dni 老扒夜夜春宵第二部的 国产在线视精品在亚洲 79电影网 口袋影院 野花手机在线观看 阿娇与冠希13分钟无删减视频 向日葵视频污 十分钟在线观看视频 kan84 身份证号码游戏注册用 浪货两个都满足不了你 p站全称叫proumb怎么进 我本港岛电影人 神都猛虎岳风小说免费 夺冠在线观看免费观看完整版 护士夜夜春宵 任你躁在线精品免费 柠檬网络电视tv 国产肥熟女视频一区二区 真人做人试看120分钟 欧美日韩无线码免费 寡妇和大狼交 保险女王 sese 绝色美艳尤物胯下娇吟 google japan 神马电影院 欧美片区 欲望妹妹 微信头像2020独一无二 父爱如山动漫 a级片 年轻的妻子 又黄又湿又免费的视频 磁力天堂torrent 秋霜在线观看高清视频 鲁青青 2012中文字幕视频 国产在线视精品在亚洲 好吊妞 顾轻舟司少帅免费阅读 啵乐腐味满满网站 国语自产拍在线视频中文 猪蜜蜜电视剧大全 国产短视频精品区 2046免费观看全集 欲望妹妹 爱情鸟免费论坛在线 graphis图片 阿娇与冠希13分钟无删减视频 五色天 受委屈离家出走被惩罚 67194在线观看免费无码 看书的网站 女主重生变娇媚体制最新章节 q友乐园个性签名 日本免费一区 顾轻舟司行霈小说全文 anquye 朋友换娶妻2完整版 青青河边草新视频免费观看 欧美色色 38节回春医疗保健操视频29分钟 清纯女友健身房被调教 苏若雪沈浪刚刚最新更新 xiao7 一胎双宝总裁大人夜夜欢全文免费阅读小说 翘着光屁股趴在办公室 香蕉一本大道中文在线 性欧美欧洲老妇 maya论坛 年轻的小峓子4中字 护士夜夜春宵 欧美日韩无线码免费 秋霞影院 sebo 粗大按摩器调教h 色五月 将夜免费神马影院影视 木瓜网 最强医圣林奇完整版 附近的人妇女 第一次破處在线国语视频播放 nana在线观看免费 宅男的天堂 苦瓜网 六漫画 国产香线蕉手机视频在线观看 爸爸的朋友 青青河边草新视频免费观看 私人拍摄 洛尘重生之都市仙尊 uoco 台湾自拍偷区亚洲综合 本草中国免费观看完整版 祖女三代共侍一夫小说 本草中国免费观看完整版 秋霞电影网鲁丝片无码2020 yh8.live樱花直播下载 薰衣草高清视频在线观看 天狼影院 老司机67194精品线观看 斗罗大陆之唐三征服比比东 宝书网 日本高清视频在线一本视频 摩天轮社区 cba直播在线观看高清 佛山房价 向日葵视频下载 韩漫无羞遮漫画免费观看 51gan 月光影视 妈妈的朋友2 亚洲丰满熟妇在线播放 中文字字幕在线中文乱码不卡 陈扬绝世高手今日更新 佛山买房 趣播 第一次玩交换真实经历 a4yy 人猿泰山h sebo 丝瓜视频污 水咲ローラ 久久中文字幕免费高清 男人a天堂2814 中文字幕午夜福利片 穿成三个男配大佬的解药 影视大全免费观看高清版 最大胆人体艺术图片 穿成三个男配大佬的解药 最大胆人体艺术图片 purnhurb官网是什么 菠萝菠萝蜜视频在线播放官网 色五月 nana高清在线观看 qimi 女神的超级赘婿赵旭全文免费阅读 小蝌蚪app下载大全小蝌蚪 恋爱的无休止境 年轻的母亲在线观看 国产精品每日更新在线 手机看片日韩国产欧美 小草免费观看在线播放 72种性姿势真人示范 将军夫人又跑了全文免费阅读 奸魔 中国雅虎 粉色视频入口 附近人妇女 白洁被双飞 最强医圣林奇 三级片在线 蝶恋 非会员试看120秒体验区 一路向西在线 同性男黄网站 妈妈的朋友4 年轻的小峓子5 欧美日韩国产无线码 蝶恋 芝麻女孩和玉米男孩 将军夫人又跑了了全文免费阅读 秋霞影院 娃嘎 泽艺 秋霞电影网午夜鲁丝片无码 闺蜜2在线观看完整版中字 佛山 快猫视频 祖女三代共侍一夫小说 赠我予白 nana在线观看高清视频 波多野结衣在线观看 车祸变傻的妈妈让我爱 成事在人电影免费观看 老扒夜夜春宵第二部的 向日葵视频污 欧美日韩无线码免费 男人a天堂2814 夫妻那些事儿免费观看 日本三级片电影 幸福花园 公憩28篇小说 斗罗大陆之征服比比东 超级女婿赵旭李晴晴全文免费阅读 kan84 青春草在线视频免费观看 28岁未成年电视免费观看 日本无码一区 狼客网 给人一种阳光的头像 向日葵视频污 情欲满载 岳风柳萱更新最快 香蕉一本大道中文在线 又黄又湿又免费的视频 年轻的母亲在线观看 人妻日本三l级香港三级 给人一种阳光的头像 五月天婷五月天综合网 uoco 父爱如山动漫 japanesefree中国寡妇 妈妈的朋友2 黄网大全 人与性 四虎最新紧急入口 元气骑士破解版下载2020最新版本 磁力天堂在线 日本不卡免费一区二区 将军夫人又跑了 最好看的2018中文字幕 都市仙尊洛尘最新章节 2012中文字幕视频 翘着光屁股趴在办公室 啵乐 07bbb 柠檬网络电视tv 姐姐的朋友3 大黄片 年轻的姐姐 赠我予白可以在哪里看 二次元超污没有衣服无遮无挡 夫妻那些事儿免费观看 美女禁区 身为人母在线观看免费 yy8098影视理论 岳风柳萱更新最快 a级片 小草在线观看视频免费2019 同性男黄网站 沈浪苏若雪最新更新章节顶点 诸天万界推倒女主角 玖玖热 车祸变傻的妈妈让我爱 67194成l人在线观看线路 草莓视频官网入口ios 久久电影网午夜鲁丝片 菠萝菠萝蜜视频在线播放官网 高清一本dvd 免费毛片在线看不用播放器 国产短视频精品区 5个小妙招巧治口腔溃疡 闪闪电影院 教授不可以全文 35pao 六漫画-免费漫画 都市仙尊洛尘全集目录 免费黄色片 顾轻舟司少帅免费阅读 原始的冲动 都是仙尊洛尘免费阅读 女主重生变娇媚体制 亚洲中文字幕永久在线 修女也疯狂电影在线看免费 202z 苏若雪沈浪刚刚最新更新 q友乐园网名 珠海电信网上营业厅 菠萝菠萝蜜播放观看在线视频 免费可以看污的完整视频网 亚洲久久综合爱久久 浮生陌 最新国自产拍在线播放 啵乐官方网站入口链接 国产亚洲日韩在线播放不卡 最新在线伦费观看中文 护士夜夜春宵 青青河边草免费观看 67194线路1(点击进入) 老奶奶rap 野花视频在线观看免费 赠我予白 免费可以看污的完整视频网 99re8热视频这在线视频 星辰影院 身为人母免费播放电影 他的小草莓 向日葵视频下载 磁力链bt磁力天堂 age动漫官方网 女人本色高清视频 日本三级片 向日葵视频下载 新翁熄粗大 38节回春医疗保健操视频29分钟 致命的你漫画在线观看全集免费 附近的妇女 2012高清国语版免费观看 纯真时代 叶凡秋沐橙小说 爱情鸟免费论坛在线 狼客网 啵乐 向日葵视频app下载 2828 春梦记高清完整版 骚虎影视 伊人色爱久久综合网 yy8098影视理论 狼客网 电影岛 cba直播在线观看高清 人与性 骚虎视频在线观看 国产 学生 国产女合集第六部 最新国自产拍在线播放 亚洲2020天天堂在线观看 黄网大全 叶凡秋沐橙 少年阿滨第3章 三级片在线 染指之后 亚洲 欧洲 日产 韩国 荡乱绝顶3p在线观看 亚洲丰满熟妇在线播放 蝶恋直播 血缘纽带啵乐腐味满满 2046免费观看全集 好男人神马影院 爱琴海论坛视频播放二 暴劫柔情在线观看免费 亚洲欧洲自拍图片专区 影视大全在线观看免费观看 超级全能学生杀猪刀 长日光阴 草柳 67194成l人在线观看线路 将军夫人又跑了 少年阿滨第3章 日本三级片电影 猪蜜蜜电视剧大全 2046免费观看全集 西游记86版全集 sese 最强医圣林奇 2020最新国产自产在线不卡 女朋友被窝里撒娇说要 偷偷藏不住新婚番外 肥肉 小说 琉璃免费观看电视剧全集 最强医圣沈风 欧美 av亚洲 av国产 制服 国产 学生 国产女合集第六部 大胸年轻继坶在线播放 麻豆传媒官网 新婚娇妻1一25李晶 拍摄指南 善良的闺蜜韩国三级 年轻母亲2 平民影院 一看就舒心的图片 一品道门免费视频日本 天狼影院手机版 叶凡秋沐橙免费阅读完整版 斗罗大陆免费看 诸天万界推倒女主角 日本laurenphilips 镇国战神叶君临免费阅读 荡乱绝顶3p在线观看 欧美色视频日本片免费 另类专区av无码 韩三千最新更新最新版 在线爱 二女共侍一夫双飞 榴莲视频下载 护士夜夜春宵 同房交换4p好爽 年轻的小峓子4中字 欧美片区 最大胆人体艺术图片 艳女伦交 国产亚洲欧美日韩一区 丹皇武帝 久久精品国产72国产精 成 人免费视频免费观看 茄子视频app下载 全彩口工番全漫画大全 茄子视频app下载 偷偷藏不住 62fan 我的老婆是冰山女总裁沈浪 新婚娇妻1一25李晶 大黄片 宅男的天堂 草柳 欧美日韩亚洲中字二区 国产精品嫩草影院 被黑化的前任们抓住了 重生之都市修仙洛尘 任你躁在线精品免费 超级女婿赵旭李晴晴全文免费阅读 250qq 温柔的谎言 电影 age动漫 艾玛影院官网 中文字字幕在线中文乱码不卡 沈风最强医圣最新章节 老子影院 日本高清视频在线一本视频 伊人色爱久久综合网 99re8热视频这在线视频 斗罗大陆免费观看完整版在线观看 1717 破膜后高清图 欧美色色 最早采用人工呼吸方法救人的医学家是 closeup毛茸茸pics大全 都市仙尊洛尘最新章节 久久精品国产72国产精 年轻的母亲在线观看 我就是王一彤 快猫下载 草柳 卡一卡二卡三免费视频 人与性 长日光阴 nana在线观看高清视频 laoyawo 淘气天尊新浪博客 叶凡秋沐橙小说笔趣阁 香蕉人人超人人超碰超国产 郑州桑拿 水咲ローラ 啵乐app 快活视频 99久久免费只有精品 女主重生变娇媚体制 色戒无删除158分钟完整版 艾玛影院官网 一路向西在线观看 北娃大王 本草中国免费观看完整版 亚洲 无码 在线 专区 善良的小峓子完整视频 日本道专区无码中文字幕 爸爸的朋友 国产 学生 国产女合集第六部 年轻母亲2 日本道专区无码中文字幕 宝书网 穿越民国泡尽美人 中国大黄页 受委屈离家出走被惩罚 都市重生修仙洛尘最新 年轻的女教师 飞极速在线 我与你的情深似海顾轻舟免费阅读 4399看片 将军夫人又跑了全文免费阅读 另类专区av无码 free性欧美极度另类 新天堂2 朋友的尤物人妻 国内少妇高清露脸精品视频 磁力天堂在线 最后的深爱免费观看 hxc freshman中学 丰满岳乱妇 国产原创剧情麻豆在线 韩漫无羞遮漫画免费观看 黑白配高清视频 囗交大图片26交 官场风云录 教授不可以全文 男生喜欢的污网站免费 母亲动漫电影在线观看 皮特影院在线观看 亚洲丰满熟妇在线播放 狐嫁女 身为人母电影在线观看 香蕉一本大道中文在线 国产亚洲日韩在线播放不卡 真人做人试看120分钟 欧美片区 陈说美食百家号 热久久视久久精品2019 伊人久久大香线蕉综合色啪 五色天 2020最新国产自产在线不卡 荷尔蒙电影网在线观看 神马电影院 啵乐app 国产目拍亚洲精品一区 久久中文字幕免费高清 2012中文字幕一页 第一精品福利导福航 2012中文字幕视频 沈浪苏若雪最新更新章节顶点 被夫好友侵犯中文字幕影音 最好看的2018中文字幕 骚虎网站 台湾自拍偷区亚洲综合 影视大全最新免费版 快猫网站入口 yh8.live樱花直播下载 猪蜜蜜电视剧大全 purnhurb官网是什么 八佰电影免费高清完整版在线观看 草莓视频黄 偷偷藏不住 全文免费 皮特影院 koogay sihu 攵女乱h 澳洲乱世情完整版免费 征兵网 色妞基地 北地胭脂 赠我予白 噜噜射 妈妈的朋友5 菠萝菠萝蜜视频在线播放官网 看书的网站 2828 年轻母亲2 35pao 成事在人电影免费观看 中文字幕 人妻熟女 meiguoshici 推拿完整版中文字幕 年轻母亲4 樱花视频 2020给个网站好人有好报 洛尘重生之都市仙尊最新章节 在线不卡日本v二区三区18 保险女王 奇米网 小草在线观看视频播放免费 草莓视频黄 小泽玛丽亚 小蝌蚪视频 沈风最强医圣最新章节 国产精品每日更新在线 章鱼搜索 洛尘重生之都市仙尊最新章节 薰衣草视频高清在线观看 野花在线观看 在线录播 超级全能学生杀猪刀 西西gogo高清大胆专业 a级片 一路向西在线观看 google japan 国产在热线精品视频99 老奶奶rap 顾轻舟 我与你的情深似海顾轻舟免费阅读 折腰蓬莱客肉肉 磁力天堂torrent kan84 小小免费视频在线观看 黄频 绿色椅子 hxc 火车上爱爱好爽好刺激 和朋友换娶妻3 yellow高清在线观看 西游记86版全集 2012中文字幕一页 顾轻舟司少帅免费阅读 山里汉宠妻无度全文免费 小蝌蚪视频 长城小队 欧美顶级情欲片 暖暖高清在线观看视频 小草在线观看视频免费2019 graphis官网 原始的冲动 久久不射 国产目拍亚洲精品一区 koogay 一本大道香蕉中文在线视频 治早迣简单快速的方法 中文字幕第一页 芝麻女孩和玉米男孩 小草在线观看视频播放免费 杂烩大乱炖目录 51gan 2020国自产拍精品网站 无尽长廊lol王者荣耀 磁力链bt磁力天堂 jazztronauts护士 国产香线蕉手机视频在线观看 柠檬tv 亚洲中文字幕在线不卡电影 啦啦啦免费高清在线视频 秋葵视频app下载 中文字幕大香视频蕉免费 kan84 致命的你 草柳 graphis图片 年轻的妻子 wuwubox 洛尘重生之都市仙尊最新章节 韩漫无羞遮漫画免费观看 白洁被双飞 8个征兆说明你怀孕了 快播盒子 白洁孙倩 世纪佳缘会员登录 车祸变傻的妈妈让我爱 中文字幕午夜福利片 bt磁力搜索天堂 都市重生修仙洛尘最新 车祸变傻的妈妈让我爱 33ee 青青河边草免费观看 麻豆传媒官网 一线高清视频观看在线 a级片 hxc 国产在热线精品视频99 艾草仙姑在线播放 沈风最强医圣最新章节 胖妹做饭视频陈说美食 顾轻舟司少帅免费阅读 最后的深爱免费观看 亚洲一日韩欧美中文字幕在线 呆萌小可爱图片 bt磁力搜索天堂 我就是王一彤 偷偷藏不住段嘉许txt 丝瓜视频污 本草中国免费观看完整版 六漫画 寡妇和大狼交 日本樱花服务器 日本大阪免费wifi 17173 欧美日韩精品一区二区在线 磁力链bt磁力天堂 成 人免费视频免费观看 穿成三个男配大佬的解药 女人艾滋病的三大症状 bm官网中文官方网 父爱如山动漫 都市仙尊洛尘最新章节 菠萝菠萝蜜播放观看在线视频 sezhan 我与你的情深似海顾轻舟免费阅读 7752 一一影视网 赠我予白 茄子短视频更懂你 肉超级多的糙汉文 试看二十分钟视频视频有声 被夫好友侵犯中文字幕影音 毛泽东思想和中国特色社会主义理论体系概论 小玲和她的公全文阅读 快喵app下载官网 同性男黄网站 2020年最新cl地址入口 啊 cao死你个浪货 爱琴海论坛视频播放二 黄频 嘟嘟动漫网 一一影视网 春意影院 哔咔漫画app下载 mayawang 皮肤黄适合穿这6个颜色 国产 学生 国产女合集第六部 哔咔漫画app下载 单身网 顾轻舟司行霈小说全文 女主重生变娇媚体制 baoyu.tv 日本一区二区 秋霞电影网午夜鲁丝片无码 中国雅虎 人妻合集500章 菠萝菠萝蜜播放观看在线视频 xiao7 未成年网
<蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <蜘蛛词>| <文本链> <文本链> <文本链> <文本链> <文本链> <文本链>